BOOST

56 Airline / Montrose

20 Miles of Improvements

 

This project is designed to benefit commuters along the 56 Airline / Montrose route between Greenspoint Transit Center and the Texas Medical Center. Construction is in progress. Some of the enhancements you will see include:

  • New or improved sidewalks along and / or near the route
  • Improved accessibility along the route with safer crossings and new ramps for wheelchair and stroller access
  • Bus shelters with lighting for improved safety and new trash cans
  • Digital, real-time bus arrival information 

Customer waiting in newly designed bus shelter as 56 Airline / Montrose bus approaches

Project Status

 

BOOST 56 Airline / Montrose Segment Map

Status

Construction is in progress.

Location

4.5 miles from Greenspoint Transit Center to West Road along Aldine Bender, Imperial Valley Drive, Northchase Drive, Greens Road and Benmar Drive.

Status

Construction is in progress by Harris County Precinct 2.

Location

2.0 miles from West Road to Gulf Bank Road along Airline Drive.

Status

Construction is in progress on Airline Drive between Gulf Bank Road and Cavalcade Street.

Location

  • 6.0 miles from Gulf Bank Road to Cavalcade Street along Airline Drive.
  • 0.4 miles from Airline Drive to Studewood Street along Cavalcade Street. 

Status

Design and construction are complete.

Location

1.5 miles from Cavalcade Street to White Oak Drive along Studewood Street.

Status

Design is complete, but construction hasn't begun.

Location

1.5 miles from White Oak Drive to Allen Parkway along Montrose Boulevard and Studemont Street.

Status

Design is in progress by The Montrose Tax Increment Reinvestment Zone (TIRZ).

Location

2.0 miles from Allen Parkway to U.S. Highway 59 along Montrose Boulevard.

Status

Design is complete, but construction hasn't begun.

Location

2.3 miles from U.S. Highway 59 to the Texas Medical Center Transit Center along Pressler Street, Main Street and Montrose Boulevard.

Questions or comments?
Questions? Comments?
Suggestions?

On our Public Comments website, choose Construction/Planning Projects > 56 Airline/Montrose BOOST Improvement Project.

 

Get Started